The following activities will be occurring over the next 2 months

May 2022 - June 2022

  • Commissioning Sidestream 

  • Final grading North of Overflow Channel & Digesters

  • Final Completion Punchlist activities

Previous activities

Apr 2022 - May 2022

  • Commissioning Sidestream

  • Final grading North of Overflow Channel & Digesters

  • Final Completion Punchlist activities

  • NOTE: We anticipate that the trail along Lee Blvd will be open and accessible to the public in June 2022. 

Previous activities

Mar 2022 - Apr 2022

  • Commissioning Solids Train (Dewatering & Sidestream)

  • Performance Testing Equipment (Centrifuges & RDTs) 

  • Final grading North of Overflow Channel & Digesters

  • Final Completion Punchlist activities

  • Substantial Completion

Previous activities

Feb 2022 - Mar 2022

  • Commissioning Solids Train (Sidestream)

  • Performance Testing Equipment

  • Final grading North of Overflow Channel & Digesters

  • Punchlist activities

  • Demobilize jobsite trailers

Previous activities

Jan 2022 - Feb 2022

  • Commissioning Solids Train

  • Performance Testing Equipment

  • Install site fencing

  • Punchlist activities

  • Demobilize jobsite trailers

Previous activities

Dec 2021 - Jan 2022

  • Commissioning Solids Train

  • Install site fencing

  • Site grading around digesters

  • Punchlist activities

  • Demobilize jobsite trailers

Previous activities

Mar - April

2020

  • Installation of interior process mechanical equipment and piping

  • Structural backfill of wastewater treatment buildings

  • Process and electrical underground utilities

  • Structural concrete for wastewater treatment basins

  • Installation of building masonry

  • Installation of precast concrete and structural metals

  • Installation of interior ductwork, electrical conduit, and plumbing piping

  • Painting of interior walls and piping

  • Installation of electrical equipment

  • Water tightness testing of water-bearing structures

  • Installation of roofing

  • Removal of the tower cranes

Previous activities

Feb - Mar

2020

  • Installation of interior process mechanical equipment and piping.

  • Structural backfill of wastewater treatment buildings

  • Process and electrical underground utilities

  • Structural concrete for wastewater treatment basins

  • Installation of building masonry

  • Installation of precast concrete and structural metals

  • Installation of interior ductwork, electrical conduit, and plumbing piping

  • Painting of interior walls

Previous activities

Jan - Feb

2020

  • Installation of interior process mechanical equipment and piping.

  • Structural backfill of wastewater treatment buildings

  • Process and electrical underground utilities

  • Structural concrete for wastewater treatment basins

  • Installation of building masonry

  • Installation of precast concrete and structural metals

  • Installation of interior ductwork, electrical conduit, and plumbing piping

  • Painting of interior walls

Previous activities

Nov - Dec

2019

  • Installation of interior process mechanical equipment and piping.

  • Structural backfill of wastewater treatment buildings

  • Process and electrical underground utilities

  • Structural concrete for wastewater treatment basins

  • Installation of building masonry

  • Installation of precast concrete and structural metals

Previous activities

Sept - Oct

2019

  • Installation of interior process mechanical equipment and piping.

  • Excavations for new wastewater treatment basins, including rock excavation

  • Structural backfill of wastewater treatment buildings

  • Process and electrical underground utilities

  • Structural concrete for wastewater treatment basins

  • Drilled piers

  • Installation of building masonry

Previous activities

Aug - Sept

2019

  • Installation of interior process mechanical equipment and piping.

  • Excavations for new wastewater treatment basins, including rock excavation

  • Structural backfill of wastewater treatment buildings

  • Process and electrical underground utilities

  • Structural concrete for wastewater treatment basins

  • Drilled piers

  • Installation of building masonry

Previous activities

July - Aug

2019

Installation of interior process mechanical equipment and piping

Excavations for new wastewater treatment basins, including rock excavation

Structural backfill of wastewater treatment buildings

Process and electrical underground utilities

Structural concrete for wastewater treatment basins

Drilled piers

Previous activities

Jun-July

2019

  • Excavations for new wastewater treatment basins, including rock excavation

  • Structural backfill of wastewater treatment buildings

  • Process and electrical underground utilities

  • Structural concrete for wastewater treatment basins

  • Drilled piers

Previous activities

May - June

2019

  • Excavations for new wastewater treatment basins, including rock excavation

  • Structural backfill of wastewater treatment buildings

  • Process and electrical underground utilities

  • Structural concrete for wastewater treatment basins

  • Drilled piers

Previous activities

Apr - May

2019

  • Excavations for new wastewater treatment basins, including rock excavation

  • Structural backfill of wastewater treatment buildings

  • Process and electrical underground utilities

  • Structural concrete for wastewater treatment basins

  • Drilled Piers

  • Truck hauling of soils offsite

Previous activities

Mar - Apr

2019

  • Excavations for new wastewater treatment basins, including rock excavation

  • Demolition of existing wastewater treatment structures

  • Structural backfill of wastewater treatment buildings

  • Process and electrical underground utilities

  • Structural concrete for wastewater treatment basins

  • Drilled piers

  • Truck hauling of soils offsite

  • Tower Crane Mobilization​

  • Tower Crane #3: March 2019

Previous activities

Feb - Mar

2019

  • Excavations for new wastewater treatment basins, including rock excavation

  • Demolition of existing wastewater treatment structures

  • Process and electrical underground utilities

  • Structural concrete for wastewater treatment basins

  • Drilled Piers

  • Truck hauling of soils offsite

  • Tower Crane Mobilization:

  • Tower Crane #3: February 2019

Previous activities

Dec 2018 - Jan 2019

  • Excavations for new wastewater treatment basins, including rock excavation

  • Demolition of existing wastewater treatment structures

  • Process and electrical underground utilities

  • Structural concrete for wastewater treatment basins

  • Drilled Piers

  • Tower Crane Mobilization:

  • Tower Crane #1: November 2018

  • Tower Crane #2: December 2018

  • Tower Crane #3: January 2019

Previous activities

Nov - Dec

2018

  • Excavations for new wastewater treatment basins, including rock excavation

  • Demolition of existing wastewater treatment structures

  • Process and electrical underground utilities

  • Structural concrete for wastewater treatment basins

  • Drilled Piers

  • Tower crane mobilization:

  • Tower Crane #1: November 2018

  • Tower Crane #2: December 2018

  • Tower Crane #3: January 2019

Previous activities

Oct - Nov

2018

  • Installation of new traffic signal at Lee Blvd. & Mission

  • Excavations for new wastewater treatment basins, including rock excavation

  • Demolition of existing wastewater treatment structures

  • Process underground utilities

  • Structural concrete for wastewater treatment basins

  • Tower Crane Mobilization:

  • Tower Crane #1: November 2018

  • Tower Crane #2: December 2018

  • Tower Crane #3: January 2019

Previous activities

Sept - Oct

2018

  • Excavations for new wastewater treatment basins, including rock excavation

  • Demolition of existing wastewater treatment structures

  • Process underground utilities

  • Structural concrete for wastewater treatment basins

  • Completion of the Overflow Channel

  • Construction of the Trailer Complex

  • Installation of new traffic signal at Lee Blvd & Mission

Previous activities

Aug - Sept

2018

  • Excavations for new wastewater treatment basins

  • Demolition of existing wastewater treatment structures

  • Process underground utilities

  • Structural concrete for wastewater treatment basins

  • Completion of the Overflow Channel and install of temporary seeding

  • Secondary entrance installation along Lee Blvd

  • Use of soccer fields north of Lee Blvd for construction storage and laydown

Previous Activitiess 

July - Aug

2018

  • Excavations for new wastewater treatment basins

  • Demolition of existing wastewater treatment structures

  • New process underground utilities

  • Structural Concrete for wastewater treatment basins

  • Finalizing decommissioning of Facility.  Close attention will be paid to demolishing structures in order to minimize odors. 

Previous Activities

June - July

2018

  • Utility relocations

  • Earthwork & Excavations

  • Decommissioning of existing plant

  • Demolition

  • Yard Piping

  • Structural Concrete

Previous Activities

May - June

2018

  • Site Fencing

  • Utility relocations

  • Earthwork

  • Demolition

  • Decommissioning of existing plant

  • 24/7 Bypass pumping to occur the week of May 14th

Previous Activities

April - May

2018

  • Site Fencing

  • Utility relocations

  • Clear and Grub

  • Earthwork

  • Demolition

  • Decommissioning of existing plant

Groundbreaking Celebration

Thursday

April 12, 2018

For more information go to press release.

Schedule

June 2022

  • Board of County Commissioners approved Guaranteed Maximum Price Number 1 with McCarthy Building Companies to procure materials for pipeline work under Foxridge Drive. Future contract amendments including installation of these materials will be considered in fall of 2022.

May 2022

  • EPA approves WIFIA loan with Johnson County.  The low-interest loan will finance 49% of the project, resulting in significant financing costs over traditional bonds.
     

  • EPA ANNOUNCES $281 MILLION WIFIA LOAN

View Full Press Release

Feb 2022

  • Board of County Commissioners authorized funding for the overall project, and authorized JCW to proceed with seeking financing for the project under the WIFIA program and other sources.

Sept 2021

Open House

  • On Sept. 29 an In-Person Open House was held at the Nelson Facility and on Sept. 30 an Online/Virtual Open House was held for those who could not come out to the in-person event.

  • The Open House was set up to inform the public about the project and to get feedback on the public priorities and concerns. 

  • For more information about the Open House goto: Engage & Connect

Milestones Reached

Overview

schedule-jan2022.jpg

updated January 2022