Where & When
What will be happening on site?
2024-25 ACTIVITY
-
CEPT Unloading Area/Nall Ave Closure - March 2024-2028
-
Temporary Site Roads - March 2024-July 2027
-
UV & Filter Concrete Structure - June 2024-Feb 2025
-
Construction Trailer Replacement
-
Headworks Concrete Structure - July 2024-May 2026
-
Road C Paving - Spring 2024
-
Mass Excavation - May 2024-August 2024
-
Digester Area Excavation, Shoring & Tank Construction - April 2024-Aug 2025
-
Administration Building (Phase1) - Structure Enclosed - July 2024-April 2025
-
Yard Pipe and Electrical Ductbanks to Continue Across Site in 2024
​
SCHEDULE
Full Schedule of facility construction.
CONSTRUCTION
What to expect during construction.
NEW FACILITY
Rendering of completed new Nelson Wastewater Treatment Facility.
Off-Site Improvements
To learn about what is happening off-site, visit: Off-Site Improvements
Project information/schedule will be updated with information throughout planning & construction. Check back for updates.