top of page

Where & When

wherewhen

What will be happening on site?

NOTICE - November 14, 2023:​ 
Trickling Filter Decommissioning
Nov. 28 – Dec. 9, 2023

​Construction of the Nelson Wastewater Treatment Facility continues.  One of the next key steps is to remove the first of the existing trickling filters.

 

The trickling filter technology is being removed because it cannot meet future water quality requirements. Trickling filters have historically been a source of odor generation and will ultimately be replaced with a modern biological nutrient removal system.

​

Details about the activity are as follows:

  • The location of this infrastructure is highlighted in yellow in the figure. 

  • Starting November 28th, the team will be demolishing the trickling filter so that future infrastructure can be built in its place.  

Nelson WWTF - update
  • ​During this period, there is an increased potential for odor generation.  The team has taken several measures to minimize this to the extent possible, including the installation of chemical systems meant to prevent the odor from occurring and scheduling to minimize the duration of the activities to the extent possible.  

  • Dates noted may need to be adjusted to due weather or other factors.​

 

Thank you for your understanding.  We will work to complete this task as quickly as possible while maintaining a safe work environment for our team and the community.

Mid to Late 2023 ACTIVITY

  • June thru August 2023 – Trailer Build Out, Utility Relocates

  • June thru August 2023 – Lower Site Yard Pipe, Utilities, Ductbanks and Grading 

  • July 2023 – Existing UV Demo  

  • August thru End of Year 2023 – New UV/Filters - Pad Preparation & Drilled Piers 

  • August thru End of Year 2023 – Temporary Waste Activated Sludge - Excavation & Structure Construction 

  • September 2023 – New Road Paving

  • End of September 2023 – Commissioning Complete - Chemically Enhanced Primary Treatment 

​

2023-07-27-Nelson-2023updates.jpg

SCHEDULE

Schedule of facility construction – 2023 elements highlighted in yellow. 

schedule
Schedule of facility construction – 2023 elements highlighted in yellow.

CONSTRUCTION

What to expect during construction.

constructon
What to expect during construction.

NEW FACILITY

Current Rendering of completed new Nelson Wastewater Treatment Facility.

newfacility
Current Rendering of completed new Nelson Wastewater Treatment Facility

Off-Site Improvements

To learn about what is happening off-site, visit: Off-Site Improvements

Project information/schedule will be updated with information throughout planning & construction. Check back for updates.

bottom of page